STEVENS PASS UPDATE (9/18/23)

Hi everyone,

We talked about alignment for the upgraded Kehr’s Chair in an earlier blog, but it’s starting to come together now with the towers in place and you can actually see its placement. The top station has shifted slightly to the right and closer to the Double Diamond lift. We graded the bottom and built a retaining wall, making room for the drive terminal, so the walk to the maze area will be shorter than it has been.

Stay tuned. Next up will be splicing the haul rope in a couple of weeks!

Thanks,

Vince